The abutments or end seats keep the beam ends dry, and provide secure anchorage to prevent their movement in use and during flood. The diagram here shows how to calculate the correct distance of the end seat from the bank.

The end dam keeps surfacing and downslope material off the beam ends.

Protecting beam ends

Various types of abutments and end seats are shown below.

Railway sleepers

In free draining ground, these can simply be embedded in a trench and securely backfilled. In heavy clay soils, excavate a drain from the trench to the ditch, so that the trench does not act as sump. Put the half sleeper in place, and backfill with free draining material.

Draining railway sleeper bearers

In places where flooding may occur, the sleepers must be secured to the ground by stakes. Always bed the sleepers on a foundation of stony material to prevent uneven settlement.

Securing sleepers with stakes

Stone and mortar

Stone abutments should be mortared to give resistance against water erosion. Use the largest stones for foundations and corners, and fill the centre with rubble. Finish with a capping of mortar and set rag bolts in position for main beam attachment.

Stone abutments

Cast concrete

A simple end seat can be made by excavating a trench and filling it with 1:4 concrete.

Cast concrete end seat

Normally a raised end seat will be required to give sufficient clearance for the beams. This should sit on a firm foundation  of bedrock or subsoil. On deep soils where this is not possible, construct foundations as shown below.

Foundation for end seat in deep soils

The large end seat with concrete foundations is cast in one piece. Excavate the foundation, assemble and oil the shuttering, and then suspend it as shown on two beams. Fill with 1:4 concrete. The shuttering can be removed and re-used.

Large end seat with concrete foundation

The shuttering for the end seat with ramp shown below can also be re-used. Use 15mm shuttering ply with 75mm x 50mm timber nailed along each edge to give extra strength. Drill as shown, for assembly with bolts 150mm long.

End seat with a ramp

Carry shuttering to site, and set in levelled foundations about 100mm deep. Oil with shuttering oil. To save concrete, the central part can be filled with gravel, rubble or rubbish such as cans and bottles. Leave at least 100mm margin at the sides and 150mm at the head wall to give an adequate thickness of concrete. Layered bottles form a very strong structure.

Saving on concrete

Alternatively, another box of shuttering with a top can be made. This acts as a liner and makes a hollow abutment.

Using double shuttering to save concrete

Fill with concrete in layers about 100mm thick and tamp to remove air bubbles. To give a neat finish, shuttering can be set into the head wall to form a recess for the main beams. Put rag bolts in place while concrete is still wet. Brush ramp to give rough surface before concrete has set.

A recess for the main beams

Cover with damp hessian or sacking to slow drying, and leave for 24-48 hours in summer, and a minimum of 48 hours in winter. Remove bolts and knock shuttering away with a mallet.

Do not concrete if frost is likely within 12 hours.

Concrete block

Alternatively, concrete blocks can be used to build the end seat. These are easier than lintels to carry on site, but are more obtrusive because of the mortar joints.

Concrete block end seat

Cast concrete steps require complex shuttering and concreting which is best left to an expert. If steps have to be made, build them out of concrete blocks, stone or wood.

H frame

Bridges crossing narrow watercourses with stable banks, such as drainage ditches on farmland, can rest on wooden H frames which are part of the bridge construction. These are simple and quick to construct.

Bridge resting on wooden H frame

Pre-cast concrete

Concrete lintels make good end seats, being of suitable dimensions and with a fairly smooth and unobtrusive finish. Holes for the main beam fixings should be drilled by an expert, using a suitable masonry drill and safety guards. If extra clearance is needed, mortar concrete blocks onto the lintel.

Concrete lintel end seats

Abutments to stream level

These can be made of stone, concrete blocks, cast concrete or concrete pipes.

If the stream level is high, construct a sandbag dam to keep the worksite dry. Excavate foundations to at least 450mm.

Sandbag dam to protect work site

The abutment must either be rounded or with wing walls to allow the smooth flow of water. Fill abutment with rubble and cap with concrete. Set rag bolts in position.

Abutments

Cast concrete abutment with wing walls.

Cast concrete abutment with wing walls

Piers

A pier may be necessary to span either a very wide shallow stream, or an asymmetrical stream valley. The two parts of the bridge superstructure should be independent, so that no stress is put on it if differential settling occurs. Piers can be built out of mortared stone, concrete blocks, cast concrete or concrete pipe. Designs are not given here because engineering advice will normally be necessary.

Piers

Fixing the main beams

Methods of fixing the main beams to the abutment or end seat are shown below. A damp-proof membrane of bituminous felt must always be placed immediately below the main beam.

Fixing to wood

Use any of the three following methods.

Fixing bridge beams to wood

Fixing to cast concrete

Screw the rag bolts through a template to ensure that the spacing is accurate.

Fixing bridge beams to cast concrete

Logs can be secured as shown.

Fixing logs

Stone and pre-cast concrete

Pre-cast concrete should be drilled in a workshop. Alternatively, galvanised straps can be used for concrete block end seats as shown here. A rock drill can be used to drill holes in rock outcrops.

Fixing to rocky outcrops

Chapters